Infograph - Cellsite.png

1. Right of Way

  • Negotiations and documentation of prospective cell site location
  • 8 permits | 1-2 months

 

2. Social Acceptability

  • Barangay resolution, Home Owners Association consent, and residents confromity
  • 5 permits | 1-2 months

 

3. Various LGU permits

  • Zoning clearance from HLURB city or municipal resolution, occupancy permit, mayor's permit

 

4. National permits

  • DENR, LLDA, CAB, DOH, PCSD, BFAR, NCP
  • 8 permits | 1-2 months

 

5. Structural permits

  • Zoning permits, locational clearance, building permit inclusive of electrical permit, sanitation permit and mechanical permit, occupancy permit
  • 3 permits | 3-5 months

 

6. Construction starts